A series of projects are stuck in site clearance, construction is not finished in Hanoi

KHÁNH AN - HỮU CHÁNH |

Hanoi - A series of projects in the city have been "stuck in place" for many consecutive years due to land clearance problems.

According to the Hanoi Department of Agriculture and Environment, there are 1,448 projects in the city under the site clearance under the 2013 Land Law and continue to implement under the 2024 Land Law, with a total area of ​​more than 12,430ha. However, the transition between the two laws has generated many problems, affecting the progress of projects.

The Tam Trinh road construction investment project in Hoang Mai district has a total investment of up to VND 3,354 billion.

The project has a total length of nearly 3.6 km. However, up to now, the contractor has only been able to construct about 800m. The reason for the slow progress of site clearance is policy problems related to compensation, site clearance and problems related to resettlement housing.

To date, the project has undergone 4 adjustments to the site handover timeline.

Nhieu cong trinh tren duong Tam Trinh chua duoc thao do, ban giao mat bang cho du an. Anh: Huu Chanh
Many works on Tam Trinh Street have not been dismantled and the site has been handed over to the project. Photo: Huu Chanh

Another project of the capital that is also facing difficulties in site clearance is the Southern Hanoi Economic Development Axis Road Project (formerly known as the Southern Axis Road Construction Investment Project of Ha Tay province).

In April 2008, the Hanoi Southern Axis Road Construction Investment Project started construction. By 2018, the project had put into operation 18.5km from Ha Dong to the end of Thanh Oai district. The remaining 23km has not been completed, including 14km in Ung Hoa district and 9km in Phu Xuyen district.

According to the Hanoi Department of Transport, with 23km of the project, 20km has been cleared; the remaining 3km (mainly in Ung Hoa district) is facing difficulties related to 23 resettlement households.

Duong truc phia Nam doan qua huyen Thanh Oai (Ha Noi) da hoan thanh. Anh: Huu Chanh
The Southern Axis Road section through Thanh Oai District (Hanoi) has been completed. Photo: Huu Chanh
Doan tuyen qua dia ban huyen Phu Xuyen va Ung Hoa dang duoc trien khai xay dung. Anh: Huu Chanh
The section passing through Phu Xuyen and Ung Hoa districts is under construction. Photo: Huu Chanh

The Lang - Hoa Lac road project extending phase 2 through Thach That district is also facing difficulties due to the transition between the 2013 Land Law and the 2024 Land Law.

The same situation also occurs with the Investment Project to build Ring Road 4 - Hanoi Capital Region. Although 98.64% of the land area has been handed over and 99.77% of the grave relocation work has been completed, up to now, there are still 10.9 hectares that have not been cleared...

According to Lao Dong in package 8, up to now, there are still two residential areas in Dai Thinh and Chu Phan communes (Me Linh district) that have not handed over the site for the project. In package No. 9, there are still land issues in three residential areas in Duc Thuong, Dong La communes (Hoai Duc) and Ha Mo commune (Dan Phuong). In the Hong Ha bridge construction area, in Hong Ha commune (Dan Phuong district) and Van Khe commune (Me Linh district), many households have not yet agreed to hand over the site.

Nha xuong va khu dan cu o xa Duc Thuong (Hoai Duc, Ha Noi) chua duoc giai phong mat bang. Anh: Huu Chanh
The factory and residential area in Duc Thuong commune (Hoai Duc, Hanoi) have not been cleared. Photo: Huu Chanh

Recently, to remove obstacles in site clearance, in order to ensure the harmony of interests between people, businesses and the State; at the same time, speed up the progress of projects being implemented, Chairman of the Hanoi People's Committee Tran Sy Thanh requested to focus on removing the biggest "bottleneck" is site clearance, directly affecting the progress of projects.

In particular, the Department of Agriculture and Environment is required to coordinate with relevant units to review and evaluate the overall implementation of site clearance for public investment projects in the city; fully synthesize difficulties and obstacles, classify them specifically into groups of problems and propose solutions to resolve them; report the results, submit to the Chairman of the City People's Committee for consideration and direction to thoroughly handle the problems and problems related to site clearance.

The leaders of Hanoi City requested to speed up the implementation progress and disbursement of key projects and projects using central budget capital. In which, focus on implementing projects on schedule, thoroughly overcome the situation of "capital waiting for projects", avoid delays in disbursement, causing waste of investment resources.

For projects that have expired by the end of 2024, investors should urgently complete the adjustment documents, submit them to competent authorities for appraisal and approval before June 30, 2025; on that basis, determine the capital demand in 2025 to implement the project according to the approved schedule.

KHÁNH AN - HỮU CHÁNH
Noticias relacionadas

Steven Nguyen y Do Nhat Hoang hablan sobre el viaje y los desafios al interpretar Mua do

|

En el programa Ca phe chieu thu 7 del periodico Lao Dong los actores Steven Nguyen y Do Nhat Hoang compartieron despues del exito de la pelicula Mua do.

Incendio en un apartamento en un edificio de apartamentos en el centro de Ciudad Ho Chi Minh

|

Ciudad Ho Chi Minh - Incendio en un apartamento en un edificio de apartamentos ubicado en la calle Pasteur barrio de Ben Nghe afortunadamente no causo victimas.

El Primer Ministro aprueba el personal para ocupar el cargo de Presidente del Comite Popular de la ciudad de Da Nang

|

El Primer Ministro aprueba los resultados de la eleccion del cargo de Presidente del Comite Popular de la ciudad de Da Nang para el Sr. Pham Duc An Vicesecretario del Comite del Partido de la Ciudad de Da Nang.

La autopista Vinh Hao - Phan Thiet muestra erosion y deslizamientos de tierra peligrosos

|

Lam Dong - En la pista de la autopista Vinh Hao - Phan Thiet se han erosionado y abiertos los dientes lo que supone un riesgo de inseguridad para los vehiculos que participan en el trafico.

Profesor asociado y doctor Tran Dinh Thien: Puede haber una situacion de ataque con noticias falsas para destruir a las empresas lideres

|

El profesor asociado y doctor Tran Dinh Thien miembro del Consejo Asesor de Politicas del Primer Ministro y ex director del Instituto de Economia de Vietnam dijo que las noticias falsas ya no son una simple 'historia de redes sociales' sino que se han convertido en un peligro para toda la economia.

Gỡ vướng giải phóng mặt bằng dự án mở rộng đường Tam Trinh

HỮU CHÁNH |

Hà Nội - Nhiều chính sách có lợi cho người dân thuộc diện giải phóng mặt bằng dự án mở đường Tam Trinh đã được cơ quan chức năng trình thành phố xem xét.

Đang giải phóng mặt bằng mở đường trung tâm Hà Nội rộng 50m

HỮU CHÁNH |

Hà Nội - Một số đoạn đang được giải phóng mặt bằng để thi công dự án Vành đai 1 đoạn Hoàng Cầu - Voi Phục, vốn đầu tư hơn 7.200 tỉ đồng sau nhiều năm chậm trễ.

Tiến độ Vành đai 4 bị ảnh hưởng do chậm giải phóng mặt bằng

Hữu Chánh |

Sau 2,5 năm khởi công, Hà Nội vẫn chưa hoàn tất giải phóng mặt bằng dự án đường Vành đai 4. Thành phố cam kết bàn giao trong quý I/2025 nhưng còn nhiều vướng mắc cần tháo gỡ.