Accelerating site clearance for the 500kV Lao Cai - Vinh Yen transmission line

NHÓM PV |

To remove difficulties and obstacles in site clearance for the Lao Cai - Vinh Yen 500kV Line project, the localities where the project passes through are urgently implementing site clearance work, ensuring construction progress according to the direction of the Government.

Establishment of a Working Group to resolve problems

The 500kV Lao Cai - Vinh Yen Power Line project has a total investment of over VND 7,410 billion with a length of 229.5km (468 locations of power pole foundations) passing through 4 provinces including: Lao Cai, Yen Bai, Phu Tho and Vinh Phuc.

Determining the importance of the Lao Cai - Vinh Yen 500kV transmission line project in ensuring national energy security, the People's Committee of Vinh Phuc province has established a Working Group to monitor, urge, and advise on resolving related problems and difficulties.

According to the report of the Department of Industry and Trade, in 5 districts where the 500kV Lao Cai ‐ Vinh Yen transmission line project passes through, there are a total of 101 electric pole foundation locations, the total area of pole foundation that needs to be permanently reclaimed is about 12.74 hectares; there are 54 households that need to be resettled; more than 97,000m2 of forest land that must be converted to another purpose.

Mr. Nguyen Van Hoang, Ngoc My commune, Lap Thach district - a household with a dragon fruit garden affected by the project - said that his family fully supports the construction of the 500kV Lao Cai - Vinh Yen line and is ready to hand over the site. However, he hopes that the authorities will consider raising the support level for dragon fruit trees to minimize economic damage, especially as the harvest season is approaching.

In Phu Tho province, the 500kV Lao Cai - Vinh Yen transmission line project passes through 3 districts: Doan Hung, Thanh Ba and Phu Ninh with a total length of 41.16km; including 95 pole foundation locations, requiring permanent land acquisition of over 10ha. Through a preliminary review, the whole province has 99 households affected by the safety corridor of the route, expected to have to be resettled.

Mr. Vu Tien Chung, Director of the Doan Hung District Land Fund Development Center, said: Up to now, the district has completed the handover of 48/48 pole foundation locations; completed the inventory of land, assets, trees, crops and issued a notice of land recovery and compensation plan estimates for households.

"Dating day, price increase night"

In Yen Bai province, up to now, 162/173 pole foundation locations have been handed over to the contractor for construction, reaching 93.6%. The handover of the route corridor is still being implemented, completing the measurement, drawing and placing boundary markers for 10/23 communes, the remaining communes are waiting for approval of documents.

To ensure the project's progress, Mr. Ngo Hanh Phuc - Vice Chairman of Yen Bai Provincial People's Committee requested investors to speed up the measurement, verification and completion of legal documents for households that have not yet agreed on compensation plans.

On the side of Lao Cai province, the leader of the Department of Natural Resources and Environment said that up to now, the editor of the records and chart of the cadastral continental deduction for land acquisition is 100/100 column position, reaching 100% of the project volume. The statistics have been completed 33/33 columns of 80 households in Bao Thang district and 67/67 columns of 118 households in Bao Yen district.

For the land area between pillars, the land area within the service road when constructing the project, the province will apply an appropriate mechanism to prevent people from being disadvantaged.

To ensure progress, the Chairman of Lao Cai Provincial People's Committee requested that the staff directly involved in site clearance work need to "rol up to work, day and night, measurement day and night; and compensation price application work to ensure publicity, transparency, and compliance with policies.

On the side of the local government, the armed forces and the youth union also took action to support people with practical actions such as moving assets, houses, trees, crops when clearing the site, supporting construction units...

To ensure the completion of the project before August 31 according to the direction of the Prime Minister, the Minister of Industry and Trade requested EVN to closely coordinate with localities, urgently complete and provide relevant documents and procedures, and agree on a compensation plan. Contractors and construction units need to increase human resources, materials, equipment, and be ready to carry out construction as soon as the site is available and conditions are met.

NHÓM PV
Noticias relacionadas

Vingroup ha presentado una demanda contra la propietaria de la cuenta de Facebook Hien Nguyen ante un tribunal en Estados Unidos

|

Vingroup demanda a la Facebooker Hien Nguyen en un tribunal estadounidense por publicar informacion falsa exigiendo el fin de la conducta y la compensacion por daños y perjuicios.

Joven muere a golpes de rayo al ver su telefono en casa

|

Ha Tinh - Un joven en la comuna de Huong Xuan mientras cargaba y veia el telefono fue repentinamente golpeado por un rayo y murio.

Se solicita al Gobierno que controle estrictamente los precios del oro y los tipos de cambio de divisas

|

El Comite Permanente del Comite de Peticiones y Supervision recomienda al Comite Permanente de la Asamblea Nacional que solicite al Gobierno que fortalezca la gestion y el control de los precios del oro y los tipos de cambio de divisas.

Nombramiento de 4 miembros del Consejo de Administracion del Banco de Politicas Sociales

|

El Primer Ministro decidio nombrar a 3 viceministros y 1 secretario del Comite Central de la Union de Jovenes que tambien ocupan el cargo de miembros del Consejo de Administracion del Banco de Politicas Sociales.

La gobernadora del Banco Estatal de Vietnam Nguyen Thi Hong es calificada A+ por Global Finance

|

El informe de clasificacion del Gobernador del Banco Central fue publicado anualmente por Global Finance desde 1994.

Phú Thọ gấp rút giải phóng mặt bằng dự án đường dây 500kV

Tô Công |

Phú Thọ - Tỉnh đang tập trung đẩy nhanh tiến độ giải phóng mặt bằng dự án Đường dây 500kV Lào Cai - Vĩnh Yên đoạn qua địa bàn.

Trước giờ G khởi công đường dây 500kV Lào Cai - Vĩnh Yên

NHÓM PV |

Dự án đường dây 500kV Lào Cai - Vĩnh Yên sẽ khởi công trong tháng 2 năm nay và hoàn thành trước ngày 2.9.

Thủ tướng dự Hội nghị tổng kết đường dây 500kV mạch 3

Cường Ngô |

Sáng 8.12, Thủ tướng Chính phủ tham dự Hội nghị tổng kết đường dây 500kV mạch 3. Dự án được khánh thành vào ngày 29.8.2024 sau hơn 6 tháng thi công thần tốc.