Removing bottlenecks, the 329 billion VND bypass in Tuyen Quang is about to reach the finish line

Việt Bắc |

After the problems with the site were resolved, the bypass route worth more than 329 billion VND in Tuyen Quang is accelerating to the finish line.

In early April 2025, the approach road and the final span on the Pho Day River overpass of the Son Duong town bypass project (Tuyen Quang) are being urgently constructed after land problems have been resolved.

According to the records, workers are focusing on completing the bridge deck and railing, while the approach road section intersecting with km188 of National Highway 37 is under construction, synchronously connecting with the bridge.

The Pho Day River Overpass Bridge with a value of over VND50 billion is the largest item in the Son Duong town bypass project, over 4km long, with a total investment of over VND329 billion. The project is invested by the Department of Transport of Tuyen Quang province (now the Department of Construction), starting construction in November 2021.

Cau vuot song Pho Day giao cat voi QL.37 giup rut ngan thoi gian tu Tuyen Quang di Thai Nguyen. Anh: Viet Bac.
The Pho Day River overpass intersecting with National Highway 37 helps shorten the time from Tuyen Quang to Thai Nguyen. Photo: Viet Bac.

In 2024, the construction area of the Pho Day River Overpass will encounter problems with the clean water pipeline of Son Duong town, so the construction must be temporarily suspended while waiting for the pipeline and underground infrastructure to be relocated.

After having the site in early 2025, the construction of the final items of the Pho Day River overpass will be resumed.

Nearby, the last 400m of this road has hard rock foundation, so the construction has to take longer than expected. Because it is near residential areas, stone breaking cannot be done with blasting and can only be drilled and bulldozed by specialized machines.

Hon 400m duong nen da cung dang duoc thi cong. Anh: Viet Bac.
More than 400m of hard rock road is under construction. Photo: Viet Bac.

Currently, the drilling and breaking of hard rock is about to be completed. A representative of the construction unit (27/7 Company Limited) said that due to the hard rock foundation, the design of some items such as positive slopes, sidewalks, drainage systems, and construction progress is being accelerated.

After more than 3 years of implementation, most of the items of the Son Duong town bypass project have been completed. The entire route has basically been paved with asphalt concrete, sidewalks, lighting systems, signs and lane markings.

Phan lon tuyen duong tranh thi tran Son Duong da hoan thanh, cho dua vao su dung.
Most of the Son Duong town bypass road has been completed and is waiting to be put into use.

The first section of the route intersecting with Km183 QL.37 has now been fenced off and warning signs have been installed to prevent vehicles from entering to ensure safety during the construction process.

According to the investor, the project has now completed over 95% of the volume. The items of the river overpass and the background of 400m at the end of the route are being accelerated. It is expected that the entire route will be completed and put into use in the second quarter.2025.

Việt Bắc
Noticias relacionadas

Limite de entrega de la linea de la autopista de Tuyen Quang - Ha Giang

|

El presidente de la Junta de la provincia de Tuen Quang pidio a los locales que terminen la entrega de toda la superficie de la autopista Tuen Quang - Ha Giang antes del 5 de abril.

La policia investiga el derribo ilegal de la cubierta de la carretera de escape

|

Las autoridades estan investigando el caso de una excavacion ilegal en la carretera de esquiva al sur de la ciudad de Bao Lac, que fue reportado por el periodico.

Tuyen Quang fijo como objetivo eliminar el refugio hace 4 meses

|

La provincia de Quang se propone eliminar las casas temporales y las casas destruidas en agosto de 2025, antes de la fecha limite de 4 meses establecida por el Gobierno.

Joven muere a golpes de rayo al ver su telefono en casa

|

Ha Tinh - Un joven en la comuna de Huong Xuan mientras cargaba y veia el telefono fue repentinamente golpeado por un rayo y murio.

Se solicita al Gobierno que controle estrictamente los precios del oro y los tipos de cambio de divisas

|

El Comite Permanente del Comite de Peticiones y Supervision recomienda al Comite Permanente de la Asamblea Nacional que solicite al Gobierno que fortalezca la gestion y el control de los precios del oro y los tipos de cambio de divisas.

Nombramiento de 4 miembros del Consejo de Administracion del Banco de Politicas Sociales

|

El Primer Ministro decidio nombrar a 3 viceministros y 1 secretario del Comite Central de la Union de Jovenes que tambien ocupan el cargo de miembros del Consejo de Administracion del Banco de Politicas Sociales.

Descubrimientos continuos de establecimientos de venta de pasteles de mediana edad de contrabando en Hanoi

|

Hanoi - El 12 de septiembre durante una inspeccion de 2 establecimientos comerciales en los distritos de Duong Noi y Phu Luong las fuerzas de QLTT descubrieron una gran cantidad de banh trung de contrabando.

La gobernadora del Banco Estatal de Vietnam Nguyen Thi Hong es calificada A+ por Global Finance

|

El informe de clasificacion del Gobernador del Banco Central fue publicado anualmente por Global Finance desde 1994.

Limite de entrega de la linea de la autopista de Tuyen Quang - Ha Giang

Việt Bắc |

El presidente de la Junta de la provincia de Tuen Quang pidio a los locales que terminen la entrega de toda la superficie de la autopista Tuen Quang - Ha Giang antes del 5 de abril.

La policia investiga el derribo ilegal de la cubierta de la carretera de escape

LAM HỒNG |

Las autoridades estan investigando el caso de una excavacion ilegal en la carretera de esquiva al sur de la ciudad de Bao Lac, que fue reportado por el periodico.

Tuyen Quang fijo como objetivo eliminar el refugio hace 4 meses

Việt Bắc |

La provincia de Quang se propone eliminar las casas temporales y las casas destruidas en agosto de 2025, antes de la fecha limite de 4 meses establecida por el Gobierno.