Public, equal selection of bauxite mining investors

BẢO LÂM |

Dak Nong - The selection of bauxite mining investors will be done publicly, equally, prioritizing modern technology and strong financial capacity.

Quarrying nearly 1.8 billion tons of bauxite ore

According to the Mineral Planning 2021 - 2030, with a vision to 2050 (Decision No. 866 dated July 18, 2023), Dak Nong owns a total reserve of nearly 1.8 billion tons of bauxite ore, accounting for more than 57% of the country's reserves.

Dak Nong has 5 clusters of mines, each cluster is built with only 1 bauxite processing factory complex. For mine cluster 1 (existing Nhan Co alumina complex), Dak Nong proposed that the Vietnam National Coal - Mineral Industries Group carry out procedures to increase the factory's capacity to 2 million tons of alumina/year.

Quarry Cluster 2, Viet Phuong Group Joint Stock Company is proposing to build an Alumina Factory complex. The total area is 441.7 hectares and the expected capacity is 1-2 million tons/year. The total estimated investment is over VND 21,000 billion.

The 3 mine cluster has two proposed enterprises: TH Group Joint Stock Company (Nam N'Jang and Truong Xuan communes, Dak Song district, 465ha) and Dong Bac Corporation (Dak N'Drung commune and Nam N'Jang, Dak Song district, 1,315ha).

At the 4th mine cluster (Tuy Duc district), Duc Giang Chemical Group Joint Stock Company proposed to build a factory in Dak Buk So commune (96ha).

Nhieu nha dau tu muon xay dung nha may che bien bo xit. Anh: Hoang Hoai
Many investors want to build bauxite processing plants. Photo: Hoang Hoai

Equality among investors

Regarding bauxite mineral exploitation, Standing Vice Chairman of Dak Nong Provincial People's Committee Le Trong Yen affirmed that all investors will be treated equally.

The selection process is based on objective factors, prioritizing modern technology, economic efficiency and strong financial capacity.

Projects must comply with the laws on enterprises, auctions, investment, bidding, land, minerals and the environment.

The projects in the planning will be handled according to the Land Law. For projects outside the planning, the construction of the factory will be considered until 2025.

Mr. Le Trong Yen emphasized that the investment policy must ensure 3 conditions: in accordance with national planning, provincial planning and regional planning.lower-level plans will be updated and adjusted to ensure consistency.

Previously, during a working trip to the Dak Nong Provincial Party Committee Standing Committee on March 1, Politburo member and Permanent Deputy Prime Minister Nguyen Hoa Binh said that bauxite is considered a beauty queen but when choosing the wrong investor, they are covered with a blanket and shelter.

Therefore, the province needs to select investors with potential, capacity, experience, professional management and implementation organizations...

BẢO LÂM
Noticias relacionadas

Dak Nong strives to start a large bauxite mining project soon

|

Dak Nong is speeding up the approval of the bauxite 2 project, with the goal of starting the Alumina plant before April 30, 2025.

Luces gigantes de la luna de miel de cientos de millones de VND brillantes en la ciudad de Tuyen Quang

|

Tuyen Quang - El festival de Trung thu en Tuyen Quang es famoso por sus enormes linternas.

No permitir la congestion de proyectos electricos debido a los retrasos en los tramites administrativos

|

El Viceprimer Ministro solicito a 3 corporaciones y 1 empresa militar que implementen resueltamente el proyecto electrico y no permitan la congestion del proyecto electrico debido a los retrasos en los procedimientos administrativos.

El marido se va a trabajar lejos la esposa en casa es infiel y tiene hijos con otra persona - Parte 1

|

Hora 9 - El marido expatriado se va a trabajar lejos y envia dinero para mantener a su familia. Pero en la soledad la esposa es infiel y esta embarazada de otra persona. ¿Como sera esta familia?

Vietnam continua contribuyendo a la paz en la frontera entre Tailandia y Camboya

|

Vietnam da la bienvenida a los desarrollos positivos entre Camboya y Tailandia y continuara esforzandose por contribuir a la paz en las fronteras de los dos paises.

El ferrocarril de metro interno de Hanoi podria extenderse hasta Ninh Binh

|

El Viceprimer Ministro Tran Hong Ha ha dado instrucciones sobre la propuesta de permitir la extension de la linea de metro intraregional desde la capital Hanoi a la provincia de Ninh Binh.

Dak Nong strives to start a large bauxite mining project soon

BẢO LÂM |

Dak Nong is speeding up the approval of the bauxite 2 project, with the goal of starting the Alumina plant before April 30, 2025.

Đắk Nông kiến nghị Trung ương gỡ khó cho các dự án bô xít

BẢO TRUNG |

Đắk Nông - Ban Thường vụ Tỉnh ủy Đắk Nông kiến nghị Trung ương gỡ khó cho các dự án khai thác bô xít tại địa phương.

Bô xít là hoa hậu nhưng chọn sai nhà đầu tư thì đắp chiếu

THANH TUẤN |

Đắk Nông - "Bô xít được coi là hoa hậu nhưng chọn nhà đầu tư không đúng thì lại đắp chăn, đắp chiếu".