Working through the ceremony, speeding up construction at key national projects

HÀ ANH CHIẾN |

In order for a series of key national transport projects such as Long Thanh airport, Bien Hoa - Vung Tau expressway, Ben Luc - Long Thanh expressway, and Ring Road 3 to be completed on time, thousands of workers are working day and night, working through the Hung Vuong Anniversary and the upcoming April 30th Anniversary.

Construction through the ceremony, organizing night work

According to the reporter of Lao Dong Newspaper, these days at the Long Thanh Airport Project construction site in Binh Son commune, Long Thanh district, despite entering the peak of the hot and dry weather in the South, thousands of officers and workers are still speeding up the construction of the "sprint" phase.

On the construction site, the construction units have mobilized hundreds of construction stitches with nearly 10,000 experts, engineers, workers, workers and nearly 3,000 construction equipment to accelerate the construction progress with the basic goal of completing the construction component before December 31, 2025 to welcome the XIV National Delegation Congress of the XIV Party; Celebrating the 80th anniversary of the National Day of the Socialist Republic of Vietnam; The 50th anniversary of the complete liberation of the South and the reunification of the country.

To ensure progress and quality, Vietnam Airports Corporation (ACV) - the investor of the Long Thanh airport component project - said it will continue to increase its forces, taking advantage of the dry season to speed up construction. In addition to construction through the ceremony, contractors also organize night work. ACV requires units to make appropriate construction plans, both ensuring progress and creating a warm working environment, showing concern for workers during the holiday.

Speaking to Lao Dong Newspaper reporter, Mr. Nguyen Duc Thuan - Deputy Executive Director of the Joint Venture for package 5.10, construction of Long Thanh airport passenger terminal - said that more than 5,000 experts, engineers, workers, and laborers are being mobilized to urgently and with quality to ensure the progress of the project, the joint venture contractor plans to construct during the holiday.

According to Lieutenant Colonel Le Van Tien - belonging to the Aviation Construction Corporation (ACC) - Commander of the Contractor Joint Venture Package 4.6, Construction of Long Thanh Airport Landing Road: The Contractor Joint Venture has planned the plan, the construction of the ceremony, the manpower of the machinery and equipment to ensure the preserving and dividing the nose to ensure the construction work and surpassing the progress.

It is known that this package is planned to complete and technically exploit the runway and taxiway before April 30, 2025, 3 months ahead of schedule.

Mr. Duong Quang Dien - Permanent Deputy Director of the Long Thanh Airport Project Management Board - said: "In 2025, we are determined to basically complete the construction work of the Long Thanh airport project, phase 1".

Mobilizing "3 shifts, 4 teams" to keep up with progress

In addition to the Long Thanh Airport Super Project, Dong Nai province is also simultaneously implementing the construction of the Bien Hoa - Vung Tau Expressway project, Ben Luc - Long Thanh Expressway, Ho Chi Minh City Ring Road 3...

For the Bien Hoa - Vung Tau expressway project, the two component projects through Dong Nai province are still slow, the locality is required to urgently complete the embankment before June 30 and the entire project before December 31, 2025. Therefore, the construction of this project is also being "taken away" by Dong Nai.

Talking to Lao Dong Newspaper reporters about this project, Mr. Nguyen Linh - Deputy Director of the Dong Nai Province Traffic Construction Investment Project Management Board - said: "We request contractors to focus on "3 shifts, 4 teams", working day, working night, working through holidays such as: Anniversary of the Anniversary, April 30, taking advantage of the favorable weather of the dry season to basically open the entire route to traffic by the end of 2025".

Lieutenant Colonel Do Van Tuan - Deputy Director of Truong Son 15 Executive Board - said that the unit regularly encourages construction workers to ensure progress and safety, and the unit also ensures full benefits for workers.

The traffic route connecting Long Thanh airport is being accelerated. Route T1 has reached more than 90% of the volume, expected to be technically open to traffic on April 30, 2025. Route T2 is over 65% complete, will start paving in June and be completed in early September 2025. Nearly 1,000 workers and machines are working day and night, striving to complete both lines 3 months ahead of schedule.

HÀ ANH CHIẾN
Noticias relacionadas

Caso de 'carta de auxilio' sospechosa de ser maltratada por su madrastra: El niño sufrio un trauma psicologico

|

Hanoi - Los familiares dijeron que en el pasado la niña H a menudo mostraba signos de panico y trauma psicologico sospechosos de ser maltratada por su madrastra.

Hoang Anh Gia Lai elimina a Thanh Hoa en la Copa Nacional

|

En la noche del 13 de septiembre Hoang Anh Gia Lai vencio a Thanh Hoa 2-0 en la fase de clasificacion para la Copa Nacional de Valores LPBank 2025-2026.

Incendio en un apartamento en un edificio de apartamentos en el centro de Ciudad Ho Chi Minh

|

Ciudad Ho Chi Minh - Incendio en un apartamento en un edificio de apartamentos ubicado en la calle Pasteur barrio de Ben Nghe afortunadamente no causo victimas.

Demanda a una empresa por deudas salariales y muchos trabajadores en Gia Lai reciben una respuesta del tribunal

|

Gia Lai - Muchos trabajadores demandan a Phuc Thinh Binh Dinh Co. Ltd. por deudas salariales y prestaciones y el tribunal les paga por no haber pasado por un proceso de mediacion obligatoria.

Profesor asociado y doctor Tran Dinh Thien: Puede haber una situacion de ataque con noticias falsas para destruir a las empresas lideres

|

El profesor asociado y doctor Tran Dinh Thien miembro del Consejo Asesor de Politicas del Primer Ministro y ex director del Instituto de Economia de Vietnam dijo que las noticias falsas ya no son una simple 'historia de redes sociales' sino que se han convertido en un peligro para toda la economia.

Quảng Ngãi sắp bổ sung ba dự án trọng điểm 25.279 tỉ đồng

VIÊN NGUYỄN |

Sắp tới, Quảng Ngãi bổ sung 3 dự án trọng điểm với tổng đầu tư 25.279 tỉ đồng, hứa hẹn thúc đẩy mạnh mẽ sự phát triển kinh tế của tỉnh.

Đắk Lắk họp bàn phương án triển khai các dự án trọng điểm

BẢO TRUNG |

Đắk Lắk - Ban Chỉ đạo 321 tỉnh yêu cầu các đơn vị liên quan tập trung tháo gỡ khó khăn, tăng tốc triển khai các dự án trọng điểm tại địa phương.

Đầu tư tín dụng hướng vào các dự án trọng điểm ở Tây Nguyên

BẢO TRUNG |

Đắk Lắk - Các tổ chức tín dụng sẽ tập trung đầu tư vào các dự án trọng điểm, thúc đẩy phát triển ngành thế mạnh Tây Nguyên.

6 dự án trọng điểm giúp TPHCM và Đồng Nai xích lại gần nhau

MINH QUÂN |

TPHCM - Cầu Cát Lái, cầu Phú Mỹ 2, cầu Đồng Nai 2, đường ven biển, đường sắt Thủ Thiêm - Long Thành và kéo dài Metro số 1 giúp tăng kết nối TPHCM và Đồng Nai.