Successfully raising the 5,300-ton steel roof to the roof of Long Thanh airport terminal

HÀ ANH CHIẾN |

Dong Nai - The steel roof structure of the central passenger terminal of Long Thanh airport with a weight of 5,330 tons has been successfully raised to the top.

On April 4, the Long Thanh Airport Project Management Board, together with the Vietur consortium, a member of the ATAD steel structure in coordination with subcontractor VSL (Switzerland), successfully upgraded the steel roof system of the Long Thanh airport passenger terminal to the top after more than 8 days, ensuring accuracy, quality, and safety.

The process of upgrading the steel roof structure of the central steel roof of Long Thanh airport with a weight of about 5,330 tons began on March 27.

According to the Long Thanh Airport Project Management Board, raising the steel roof of the central passenger terminal is a particularly important task, deciding the progress of package 5.10 - passenger terminal.

Because the central steel roof structure system has a very large weight, the raising process of units uses a combination of pulling and pushing solution using a hydraulic shock absorber system; using a computer system to monitor the load and related problems.

The roof raising is done in many steps to test the load, regulate techniques, and ensure absolute accuracy.

After successfully raising the steel roof, the units continue to focus on speeding up the construction progress and installing equipment at the Long Thanh airport passenger terminal.

The passenger terminal is the most important item in the Long Thanh airport project, deciding the progress of the entire project on the gantt road.

Currently, Long Thanh airport passenger terminal has completed the reinforced concrete structure of the underground part and floors (4 floors), is installing steel structure, glass walls, and terminal equipment; by the end of December 2025, the terminal will basically complete construction.

The roof system is divided into many large modules for assembly underground, then lifted. Each modular must be assembled accurately, ensuring no deformation when under pressure during the lifting process. The roof has a curved, wavy structure, with many layers stacked, simulating lotus petals, requiring detailed 3D modeling and accurate calculation to ensure consistency with the overall architecture. This not only requires high aesthetics but also meets the strict technical requirements of an international airport that meets 4F standards according to the International Aviation Organization (ICAO).

HÀ ANH CHIẾN
Noticias relacionadas

Dong Nai despejo 3 carreteras que conectan a aeropuerto Long Thanh

|

Dong Nai requiere que 6 distritos y ciudades despeguen urgentemente el sitio de 3 proyectos de DT 770B Road, DT 773 Road, DT 769 Road que conecta Long Thanh Airport.

Polonia despliega 40.000 soldados cerca de la frontera la tension en Europa del Este alcanza niveles alarmantes

|

Polonia envia 40.000 soldados cerca de la frontera en un contexto en el que Rusia y Bielorrusia llevan a cabo los ejercicios Zapad 2025 elevando las tensiones en Europa del Este a niveles alarmantes.

Cerca de 1.600 estudiantes en la comuna montañosa de Son La siguen aislados debido a los deslizamientos de tierra

|

Son La - Han pasado mas de 10 dias la carretera principal en la comuna de Tuong Ha que sufrio deslizamientos de tierra aun no se ha reparado miles de estudiantes y personas todavia estan aislados.

El trabajo de formacion de voleibol juvenil en Vietnam necesita un gran avance

|

El trabajo de seleccion y formacion de jovenes atletas de voleibol vietnamitas enfrenta muchas dificultades por razones objetivas y subjetivas.

Dong Nai despejo 3 carreteras que conectan a aeropuerto Long Thanh

HÀ ANH CHIẾN |

Dong Nai requiere que 6 distritos y ciudades despeguen urgentemente el sitio de 3 proyectos de DT 770B Road, DT 773 Road, DT 769 Road que conecta Long Thanh Airport.

Đưa vụ vi phạm đền bù sân bay Long Thành vào diện theo dõi

MINH CHÂU |

Đồng Nai - Ban Chỉ đạo phòng chống tham nhũng, lãng phí, tiêu cực tỉnh đưa vụ án vi phạm đền bù tại dự án sân bay Long Thành vào diện theo dõi.

Thủ tướng lì xì cho công nhân thi công sân bay Long Thành

HÀ ANH CHIẾN - NHƯ QUỲNH |

Đồng Nai – Thủ tướng Chính phủ Phạm Minh Chính chúc Tết, tặng quà, lì xì cho các cán bộ, kỹ sư và công nhân đang thi công xuyên Tết ở sân bay Long Thành.