Panorama of raising the steel roof of Long Thanh airport terminal weighing 5,300 tons using a pull-up and push-up solution

HÀ ANH CHIẾN (Ảnh, video: Tổng Công ty Cảng hàng không Việt Nam (ACV) cung cấp) |

Dong Nai - The steel roof of the Long Thanh airport passenger terminal weighing 5,300 tons was successfully lifted with a towing and pushing solution using a hydraulic shock system.

h1
On April 4, in Dong Nai, Vietur consortium, contractor of package 5.10 "Construction and installation of equipment for passenger terminal works", steel structure member ATAD coordinated with subcontractor VSL to successfully upgrade the steel roof structure of Long Thanh International Airport (abbreviated as Long Thanh airport) by combining the solution of pulling and pushing with the hydraulic shock system (Lifting) after more than 8 days, ensuring accuracy, quality, and safety.
h2
The total weight of the steel roof is up to more than 5,300 tons, assembled from 256 connection points, meeting European control standards. The roof has a curved arch structure with an area of nearly 20,000 m2, including a cantilever (cantilever) up to 41 m long that emerges. The entire giant structure is powered by 56 specialized hydraulic shock devices, each of which can withstand a load of 40 to 330 tons, helping to ensure a safe and accurate installation process.
h3
According to the Vietnam Airport Corporation (ACV), the successful increase in the steel structure system of the passenger terminal is an important milestone in the construction progress of Long Thanh Airport project, as concluded by the Ministry of Construction: "To ensure the progress of the passenger terminal, the steel structure of the station center is extremely important, deciding on the progress of the whole project. This is also a symbol of technical progress in Vietnam's construction industry, proving the management capacity of the Long Thanh Airport Project Management Board as well as the technical level of the Vietnamese engineer team not inferior to advanced countries in the world.
h4
The roof system is divided into many large modules for assembly underground, then lifted. Each modular must be assembled accurately, ensuring no deformation when under pressure during the lifting process. The roof has a curved, wavy structure, with many layers stacked, simulating lotus petals, requiring detailed 3D modeling and accurate calculation to ensure consistency with the overall architecture. This not only requires high aesthetics but also meets the strict technical requirements of an international airport that meets 4F standards according to the International Aviation Organization (ICAO).
h5
The technical research, design and preparation of solutions were carried out by the Long Thanh Airport Project Management Board together with the Vietur - ATAD consortium of engineers throughout the 12 months before the construction.
h6
Passenger terminal is the most important category at Long Thanh Airport Construction Project. Currently, the station has completed the reinforced concrete structure of the underground part and floors (4 floors), which is installing steel structure, glass wall surface, station equipment; At the end of December 2025, the passenger terminal will basically complete the construction component.
h7
The Long Thanh airport construction project is simultaneously implementing bidding packages, in which the runway and connecting traffic route (route T1) will be completed and technically exploited by the end of April 2025, 3 months ahead of schedule. Bidding packages such as: garages, aircraft fuel supply systems, and inland transport are being accelerated, basically completed by the end of this year - 2025.
h8
Mr. Duong Quang Dien - Permanent Deputy Director of the Long Thanh Airport Project Management Board said: "In 2025, we are determined to basically complete the construction work of the Long Thanh Airport Project Phase 1".
h9
According to ACV, on the construction site, construction units have mobilized hundreds of construction stitches with nearly 10,000 experts, engineers, workers, workers and nearly 3,000 construction equipment to accelerate the construction progress with the basic goal of completing the construction component before December 31, 2025 to welcome the 11th National Delegation Congress of the Party; Celebrating the 80th anniversary of the National Day of the Socialist Republic of Vietnam; The 50th anniversary of the complete liberation of the South and the reunification of the country.
The clip records the process of successfully raising the steel roof structure of the Long Thanh International Airport's central passenger terminal.

HÀ ANH CHIẾN (Ảnh, video: Tổng Công ty Cảng hàng không Việt Nam (ACV) cung cấp)
Noticias relacionadas

Successfully raising the 5,300-ton steel roof to the roof of Long Thanh airport terminal

|

Dong Nai - The steel roof structure of the central passenger terminal of Long Thanh airport with a weight of 5,330 tons has been successfully raised to the top.

Dong Nai despejo 3 carreteras que conectan a aeropuerto Long Thanh

|

Dong Nai requiere que 6 distritos y ciudades despeguen urgentemente el sitio de 3 proyectos de DT 770B Road, DT 773 Road, DT 769 Road que conecta Long Thanh Airport.

Primer plano de la fuga del sospechoso del asesinato de Charlie Kirk

|

Los investigadores estadounidenses estan pidiendo ayuda al publico para encontrar al asesino del activista de derecha Charlie Kirk.

Polonia despliega 40.000 soldados cerca de la frontera la tension en Europa del Este alcanza niveles alarmantes

|

Polonia envia 40.000 soldados cerca de la frontera en un contexto en el que Rusia y Bielorrusia llevan a cabo los ejercicios Zapad 2025 elevando las tensiones en Europa del Este a niveles alarmantes.

Cerca de 1.600 estudiantes en la comuna montañosa de Son La siguen aislados debido a los deslizamientos de tierra

|

Son La - Han pasado mas de 10 dias la carretera principal en la comuna de Tuong Ha que sufrio deslizamientos de tierra aun no se ha reparado miles de estudiantes y personas todavia estan aislados.

El trabajo de formacion de voleibol juvenil en Vietnam necesita un gran avance

|

El trabajo de seleccion y formacion de jovenes atletas de voleibol vietnamitas enfrenta muchas dificultades por razones objetivas y subjetivas.

El FBI ofrece una recompensa de 100.000 dolares por rastrear al asesino de su aliado Trump

|

El FBI esta llevando a cabo una busqueda en linea por todo Estados Unidos para encontrar al asesino Charlie Kirk aliado del presidente Donald Trump.

Successfully raising the 5,300-ton steel roof to the roof of Long Thanh airport terminal

HÀ ANH CHIẾN |

Dong Nai - The steel roof structure of the central passenger terminal of Long Thanh airport with a weight of 5,330 tons has been successfully raised to the top.

Dong Nai despejo 3 carreteras que conectan a aeropuerto Long Thanh

HÀ ANH CHIẾN |

Dong Nai requiere que 6 distritos y ciudades despeguen urgentemente el sitio de 3 proyectos de DT 770B Road, DT 773 Road, DT 769 Road que conecta Long Thanh Airport.

Thủ tướng lì xì cho công nhân thi công sân bay Long Thành

HÀ ANH CHIẾN - NHƯ QUỲNH |

Đồng Nai – Thủ tướng Chính phủ Phạm Minh Chính chúc Tết, tặng quà, lì xì cho các cán bộ, kỹ sư và công nhân đang thi công xuyên Tết ở sân bay Long Thành.