Construction through ceremony to make up for the slow progress of the expressway project through Dong Nai

HÀ ANH CHIẾN |

Dong Nai - Bien Hoa - Vung Tau Expressway and Ho Chi Minh City Ring Road 3 are under construction during the Hung Vuong Commemoration Ceremony to make up for the delay in progress of these two previous projects.

Construction offset the progress of Bien Hoa - Vung Tau Expressway

In Dong Nai, the Bien Hoa - Vung Tau expressway project is behind schedule, the locality is required to urgently complete the embankment before June 30 and the entire project before December 31, 2025. Therefore, the construction of this project is also being " sprayed" by Dong Nai, organizing construction through the ceremony.

Speaking to Lao Dong newspaper reporters, Mr. Nguyen Linh - Deputy Director of the Dong Nai Province Traffic Construction Investment Project Management Board - said: In 2 national key projects invested by the unit, including Component Project 1 - Bien Hoa - Vung Tau Expressway and Component Project 3 - Ho Chi Minh City Ring Road 3, contractors maintained construction throughout the 3 days of the Hung Kings' Commemoration Day holiday in 2025 with the goal of speeding up progress, compensating for the previously delayed progress of these 2 projects.

Cac du an giao thong trong diem o Dong Nai thi cong xuyen le Gio to Hung Vuong nam 2025. Anh: HAC
Key transport projects in Dong Nai will be constructed during the Hung Vuong Commemoration Ceremony in 2025. Photo: HAC

Component project 1 - Bien Hoa - Vung Tau Expressway has 2 main construction packages. Contractors are deploying 34 construction teams, with about 250 motorbikes and equipment, 100 engineers and more than 400 workers participating in the construction site.

Meanwhile, Component Project 3 - Ho Chi Minh City Ring Road 3 has 3 main construction packages. In this project, contractors are arranging about 23 construction teams with more than 160 locomotives and equipment of all kinds mobilized to the construction site to serve the construction.

Mr. Nguyen Dinh Kien - a worker working at package 18 of the Bien Hoa - Vung Tau expressway, from Nghe An province - shared that to ensure the project progress is very urgent, he tries to strive for the tasks assigned by superiors.

Many projects to open to traffic, technical traffic opening on April 30

At the Component 1A project of Ho Chi Minh City Ring Road 3, the Nhon Trach bridge project across Dong Nai River, connecting Thu Duc City (HCMC) with Nhon Trach District (Dong Nai Province) is also planned to be technically opened to traffic before the April 30 holiday. Therefore, the investor and contractor also mobilized construction forces throughout the Hung Vuong Ancestor's death anniversary to race for progress, completing the bridge deck to soon open the technical traffic.

Component project 1A of Ho Chi Minh City Ring Road 3 has a total length of 8.22 km, passes through Dong Nai 6.3 km and passes through Ho Chi Minh City 1.92 km. Of which, Nhon Trach Bridge is 2.6 km long, the scale of phase 1 includes 4 lanes for motor vehicles and 2 lanes for mixed vehicles. This is a key project, playing a role in connecting the region, shortening travel time from Ho Chi Minh City to Dong Nai and neighboring localities.

When the entire component project 1A of Ho Chi Minh City Ring Road 3 is put into operation, it will connect with component project 3 of Ho Chi Minh City Ring Road 3 (Dong Nai province section), leading to Ben Luc - Long Thanh Expressway, divided into the Ho Chi Minh City - Long Thanh - Dau Giay Expressway and National Highway 51.

Thi cong goi thau 5.10 nha ga hanh khach san bay Long Thanh. Anh: HAC
Construction of package 5.10 of Long Thanh airport passenger terminal. Photo: HAC

In addition to the projects of Ring Road and Expressway, at the ceremony, at Long Thanh Airport Project (Dong Nai), the main bidding packages were also constructed through the ceremony. Vietnam Airport Corporation (ACV) - Investor of component project 3 of Long Thanh Airport - said, on the construction site, construction units have mobilized hundreds of construction stitches with nearly 10,000 experts, engineers, workers, workers and nearly 3,000 construction equipment to accelerate construction progress.

In particular, package 5 - construction of Long Thanh airport passenger terminal, has more than 5,000 experts, engineers, workers and laborers being mobilized for urgent construction throughout the holiday. Similarly, package 4.6 - construction of the Long Thanh airport runway is also under construction through the ceremony in time for the technical exploitation of the runway and taxiway before April 30.

HÀ ANH CHIẾN
Noticias relacionadas

Garment company in Dong Nai rewards 2,300 workers for Hung Vuong's Commemoration Day holiday

|

Dong Nai - Dong Phu Cuong Joint Stock Company's Trade Union awarded 2,300 workers on the occasion of Hung Vuong's Commemoration Day with a total amount of 440.5 million VND.

Luces gigantes de la luna de miel de cientos de millones de VND brillantes en la ciudad de Tuyen Quang

|

Tuyen Quang - El festival de Trung thu en Tuyen Quang es famoso por sus enormes linternas.

No permitir la congestion de proyectos electricos debido a los retrasos en los tramites administrativos

|

El Viceprimer Ministro solicito a 3 corporaciones y 1 empresa militar que implementen resueltamente el proyecto electrico y no permitan la congestion del proyecto electrico debido a los retrasos en los procedimientos administrativos.

Ciudad Ho Chi Minh fuertes lluvias prolongadas muchas carreteras inundadas profundamente arboles caidos

|

Ciudad Ho Chi Minh - La lluvia de la tarde del 11 de septiembre que duro hasta la noche en Ciudad Ho Chi Minh ha provocado inundaciones profundas y congestion en muchas carreteras.

El marido se va a trabajar lejos la esposa en casa es infiel y tiene hijos con otra persona - Parte 1

|

Hora 9 - El marido expatriado se va a trabajar lejos y envia dinero para mantener a su familia. Pero en la soledad la esposa es infiel y esta embarazada de otra persona. ¿Como sera esta familia?

Vietnam continua contribuyendo a la paz en la frontera entre Tailandia y Camboya

|

Vietnam da la bienvenida a los desarrollos positivos entre Camboya y Tailandia y continuara esforzandose por contribuir a la paz en las fronteras de los dos paises.

La Confederacion General del Trabajo de Vietnam guia sobre la recaudacion de fondos sindicales

|

Los sindicatos de base utilizan el 75% de la recaudacion total de fondos sindicales de acuerdo con el documento de orientacion de la Confederacion General del Trabajo de Vietnam.

El Secretario del Comite del Partido de la Ciudad de Ho Chi Minh Tran Luu Quang tiene mas tareas importantes

|

TPHCM - El Secretario del Comite del Partido de la Ciudad de Ho Chi Minh Tran Luu Quang ocupa el cargo de Jefe del Comite Directivo para la Prevencion y Lucha contra la Corrupcion el Despilfarro y la Negatividad de la Ciudad de Ho Chi Minh.

Garment company in Dong Nai rewards 2,300 workers for Hung Vuong's Commemoration Day holiday

HÀ ANH CHIẾN |

Dong Nai - Dong Phu Cuong Joint Stock Company's Trade Union awarded 2,300 workers on the occasion of Hung Vuong's Commemoration Day with a total amount of 440.5 million VND.

Sắp thông xe 33km cao tốc nối Long An - TPHCM - Đồng Nai

MINH QUÂN |

TPHCM - Dịp 30.4, có thêm 33km cao tốc Bến Lức - Long Thành được đưa vào khai thác, giúp tăng kết nối TPHCM, Long An, Đồng Nai, rút ngắn thời gian di chuyển.

Dự án đường nối Đồng Nai với cao tốc đi TPHCM vướng mặt bằng

HÀ ANH CHIẾN |

Đồng Nai - Dự án đường Hương lộ 2 - đoạn 1 dài gần 2km nhằm kết nối cao tốc TPHCM - Long Thành - Dầu Giây đang vướng 250m dài mặt bằng.