HCMC tightens disbursement discipline, sets breakthrough target

MINH QUÂN |

Ho Chi Minh City is promoting drastic measures to promote the disbursement of public investment capital in 2025, with the goal of achieving a disbursement rate of over 95%.

According to Ms. Le Thi Huynh Mai - Director of the Ho Chi Minh City Department of Finance, the total public investment capital in 2025 that the Government assigned to the city is VND84,149 billion.

However, as of March 14, 2025, the disbursed capital has only reached VND 2,555 billion, equivalent to about 3% of the total annual plan.

Previously, the Ho Chi Minh City People's Committee set a disbursement target for each quarter, in which the first quarter must reach at least 7.5%, striving for 10% or more; the second quarter must be at least 25%, aiming for 30% or more; the third quarter must not be below 50%, with the target of 70% or more; and the fourth quarter must complete at least 95%, striving for 100%.

Recently, Chairman of the Ho Chi Minh City People's Committee Nguyen Van Duoc has directed the Department of Home Affairs to coordinate with the Department of Finance, the Department of Natural Resources and Environment and the State Treasury of Region II to propose forms of handling for responsible organizations and individuals if there is a slow disbursement situation.

Units with a disbursement rate lower than the city's general target in each quarter will be criticized. In case the whole year does not meet the target or for two quarters or more it does not meet, the unit's leaders will be reviewed and reprimanded.

At the same time, relevant agencies and units need to clearly report the responsibilities of organizations and individuals when there are delays, consider handling them according to the Party's regulations on waste.

The Ho Chi Minh City People's Committee has also just established a working group to promote the disbursement of public investment capital, headed by Vice Chairman of the Ho Chi Minh City People's Committee Bui Xuan Cuong.

The task of the working group is to direct the implementation of regulations, resolutions and plans related to public investment; remove difficulties, speed up construction progress, complete settlement and establish ownership after settlement.

The working group is also responsible for monitoring, inspecting, and supervising the progress of projects; proactively urging and resolving arising problems.

Thi cong nut giao Vanh dai 3 TPHCM va cao toc TPHCM - Long Thanh. Anh: Minh Quan
Construction of the Ho Chi Minh City Ring Road 3 intersection and the Ho Chi Minh City - Long Thanh Expressway. Photo: Minh Quan

To speed up the progress of public investment disbursement, Director of the Ho Chi Minh City Department of Finance Le Thi Huynh Mai said that the city needs to direct special implementation of major projects, including: Ho Chi Minh City - Moc Bai Expressway, Xuyen Tam canal project, four BOT projects to upgrade and expand National Highways 1, 13, 22, the North - South axis road, according to the mechanism of Resolution 98.

Regarding investment preparation, the Ho Chi Minh City Department of Finance proposed to assign all Group B and C projects to the People's Committees of districts, towns and Thu Duc City for implementation, except for projects with a scope related to two or more district-level administrative units.

Specialized Project Management Boards will undertake national key projects and group A projects.

In particular, the department proposed to innovate the appraisal process, instead of separating it as before, the specialized department will appraise everything from the policy to the project content, to shorten the time and avoid overlap in management.

Speaking at a recent socio-economic meeting, Ho Chi Minh City Party Secretary Nguyen Van Nen frankly acknowledged: "Disbursement of public investment capital has not created a breakthrough, although the city has prepared and determined for many years".

Mr. Nguyen Van Nen emphasized that public investment is an important pillar to promote economic growth. Therefore, Ho Chi Minh City needs to view it objectively, thoroughly and fairly, drawing profound lessons to propose more practical and effective solutions in the second quarter and the remaining quarters of the year.

MINH QUÂN
Noticias relacionadas

4 key projects to rescue traffic jams in Ho Chi Minh City are delayed due to land clearance problems

|

HCMC - Expanding Hanoi Highway and National Highway 1, My Thuy intersection, An Phu intersection, expanding National Highway 50 are 4 projects to rescue traffic jams but are delayed due to land clearance problems.

El tunel de 343 millones de dolares en la entrada este de la capital esta a punto de entrar en transito

|

TPHCM - El tunel de 760 metros de largo, 4 carriles de dos vias, que conecta la autopista TPHCM - Long Thanh con la carretera de Mai Chi Thong, ha alcanzado mas del 90% y se espera que el trafico este en marcha el 30 de abril de 2025.

G-Dragon cierra el calendario de conciertos en Hanoi

|

La informacion recien anunciada por G-Dragon hace que la comunidad de fans en Vietnam se sienta inquieta.

Polonia despliega 40.000 soldados cerca de la frontera la tension en Europa del Este alcanza niveles alarmantes

|

Polonia envia 40.000 soldados cerca de la frontera en un contexto en el que Rusia y Bielorrusia llevan a cabo los ejercicios Zapad 2025 elevando las tensiones en Europa del Este a niveles alarmantes.

Da Nang planea tener un Secretario del Comite del Partido de la Ciudad y cinco Subsecretarios para el mandato 2025-2030

|

Da Nang - 75 miembros del Comite Ejecutivo del Partido de Da Nang estan previstos para participar en el Comite Ejecutivo del Partido de Da Nang para el mandato 2025-2030 de los cuales 73 se reelejan.

Cerca de 1.600 estudiantes en la comuna montañosa de Son La siguen aislados debido a los deslizamientos de tierra

|

Son La - Han pasado mas de 10 dias la carretera principal en la comuna de Tuong Ha que sufrio deslizamientos de tierra aun no se ha reparado miles de estudiantes y personas todavia estan aislados.

El trabajo de formacion de voleibol juvenil en Vietnam necesita un gran avance

|

El trabajo de seleccion y formacion de jovenes atletas de voleibol vietnamitas enfrenta muchas dificultades por razones objetivas y subjetivas.

4 key projects to rescue traffic jams in Ho Chi Minh City are delayed due to land clearance problems

MINH QUÂN |

HCMC - Expanding Hanoi Highway and National Highway 1, My Thuy intersection, An Phu intersection, expanding National Highway 50 are 4 projects to rescue traffic jams but are delayed due to land clearance problems.

El tunel de 343 millones de dolares en la entrada este de la capital esta a punto de entrar en transito

MINH QUÂN |

TPHCM - El tunel de 760 metros de largo, 4 carriles de dos vias, que conecta la autopista TPHCM - Long Thanh con la carretera de Mai Chi Thong, ha alcanzado mas del 90% y se espera que el trafico este en marcha el 30 de abril de 2025.

Chủ tịch TPHCM mạnh tay kiểm điểm 18 đơn vị giải ngân thấp

MINH QUÂN |

TPHCM - 7 ban quản lý dự án và 11 địa phương giải ngân dưới 95% năm 2024 phải khẩn trương kiểm điểm, làm rõ trách nhiệm và xử lý nghiêm theo quy định.