Accelerating the construction of Hanoi Ring Road 4, many sections have been revealed

HỮU CHÁNH |

Hanoi - The packages of the Ring Road 4 parallel road project are being accelerated to complete in 2025.

According to Lao Dong in package No. 9 - construction of the Ring Road 4 parallel road through Dan Phuong and Hoai Duc districts (51km long) constructed by contractor Vinaconex, dozens of locomotives and a team of officers, engineers and workers were mobilized to work continuously "3 shifts, 4 teams".

Talking to reporters, Mr. Nguyen Hoang Hai - Commander of package No. 9 - said that up to now, the package implemented by Vinaconex has reached about 56% of the contract value.

The contractor has completed the paving of about 19km of single-line road, the remaining sections are being paved with crushed stone. Some items of the canal overpass are also being urgently completed.

Vanh dai 4 doan qua huyen Dan Phuong (Ha Noi) da duoc tham nhua mat duong. Anh: Huu Chanh
The parallel road of Ring Road 4 through Dan Phuong District (Hanoi) has been paved with asphalt. Photo: Huu Chanh

Mr. Hai added that for key projects such as Ring Road 4, contractors need to make the most of favorable weather conditions, increase overtime and overtime.

"Although it is difficult, the entire team of engineers and workers are united and determined to complete the project on schedule" - Mr. Hai emphasized.

s
The factory and a residential area in Duc Thuong commune, Hoai Duc have not been cleared. Photo: Huu Chanh

Regarding site clearance, Mr. Hai informed that in package No. 9, there are still 3 residential areas in Duc Thuong, Dong La communes (Hoai Duc) and Ha Mo commune (Dan Phuong).

"Currently, relevant units are relocating underground and above-ground technical infrastructure to hand over the site to the contractor. However, for these 3 residential areas, we do not know the date when the site will be handed over to continue construction of the project" - Mr. Nguyen Hoang Hai said.

Cong truong du an duong Vanh dai 4 doan qua xa, huyen Hoai Duc. Anh: Huu Chanh
Construction site of the Ring Road 4 project through Duc Thuong commune, Hoai Duc district. Photo: Huu Chanh
May moc, cong nhan dang trien khai hang muc rai cap phoi da dam. Anh: Huu Chanh
Machinery and workers are implementing the crushed stone allocation project. Photo: Huu Chanh
Nhieu may moc, cong nhan lam viec tren cong truong du an. Anh: Huu Chanh
Many machines and workers are working at the project site. Photo: Huu Chanh

In package No. 8, according to Mr. Nguyen Hoai Nam - Head of Technical Department, Construction Management Board of Ring Road 4 in the Capital Region, Truong Son Construction Corporation - the package has a total length of about 23km, of which about 20km of parallel roads have been paved with asphalt.

Package 8 also undertakes the construction of 3 overpasses on the route including the Ca Lo River overpass connecting Soc Son with Me Linh, the Hanoi - Lao Cai railway overpass and the Hau village bridge.

Cong nhan thi cong hang muc cau vuot song Ca Lo noi huyen Me Linh va Soc Son. Anh: Huu Chanh
Workers constructing the Ca Lo river overpass project connecting Me Linh and Soc Son districts. Photo: Huu Chanh

Regarding the progress of package No. 8, Mr. Nam said that up to this point, the contractor consortium has completed about 70% of the construction volume, ensuring progress compared to the plan.

According to Mr. Nguyen Hoai Nam, there are still 2 residential areas in Dai Thinh and Chu Phan communes (Me Linh) that have not been handed over.

"For the sections that have cleared the ground, the consortium of contractors is committed to completing the Ring Road 4 parallel road section through Me Linh and Soc Son in 2025" - Mr. Nam affirmed.

Cau vuot duong sat thuoc goi thau so 8 cung dang duoc thi cong hoan thien. Anh: Huu Chanh
The railway overpass under package 8 is also under construction. Photo: Huu Chanh

In package No. 10 (through Ha Dong district and Thanh Oai district) and package No. 11 (through Thuong Tin district), contractors are also speeding up the construction progress to ensure the progress of the entire route.

The Ring Road 4 project in the Capital Region started construction in June 2023, with a total length of 112.8km, passing through Hanoi, Hung Yen and Bac Ninh, with a total investment of more than VND 85,000 billion.

In Hanoi alone, the route is more than 57km long, passing through the districts: Ha Dong, Soc Son, Me Linh, Dan Phuong, Hoai Duc, Thanh Oai and Thuong Tin.

After 21 months since the groundbreaking date, 4 construction packages in Hanoi have been deployed simultaneously over a length of more than 48km, with 32 construction teams (including 23 road construction teams and 9 bridge construction teams).

Hanoi City aims to complete all site clearance work before April 15 and put the parallel road into operation in October 2025, welcoming the City Party Congress.

HỮU CHÁNH
Noticias relacionadas

Hanoi tiene dos semanas para entregar la tierra suficiente para la carretera de la Franja 4

|

Hanoi - Los distritos y distritos deben completar la liberacion de la superficie del proyecto de la Zona 4 antes del 15.4 bajo la direccion del Presidente de la Junta de la ciudad.

Puente sobre el rio, ferrocarril en la Zona 4 de Hanoi en forma

|

Hanoi - Tres puentes que cruzan el rio, el proyecto de ferrocarril de la ruta paralela de la Franja de 4 tramos a traves del distrito de Meilin ya ha aparecido y esta siendo terminado.

El trabajo de formacion de voleibol juvenil en Vietnam necesita un gran avance

|

El trabajo de seleccion y formacion de jovenes atletas de voleibol vietnamitas enfrenta muchas dificultades por razones objetivas y subjetivas.

Ex presidente de Brasil sentenciado a 27 años de prision por conspirar para un golpe de estado

|

El Tribunal Supremo de Brasil condeno al ex presidente Jair Bolsonaro por conspiracion para derrocar los resultados electorales de 2022 a una pena de 27 años de prision.

Luces gigantes de la luna de miel de cientos de millones de VND brillantes en la ciudad de Tuyen Quang

|

Tuyen Quang - El festival de Trung thu en Tuyen Quang es famoso por sus enormes linternas.

No permitir la congestion de proyectos electricos debido a los retrasos en los tramites administrativos

|

El Viceprimer Ministro solicito a 3 corporaciones y 1 empresa militar que implementen resueltamente el proyecto electrico y no permitan la congestion del proyecto electrico debido a los retrasos en los procedimientos administrativos.

El marido se va a trabajar lejos la esposa en casa es infiel y tiene hijos con otra persona - Parte 1

|

Hora 9 - El marido expatriado se va a trabajar lejos y envia dinero para mantener a su familia. Pero en la soledad la esposa es infiel y esta embarazada de otra persona. ¿Como sera esta familia?

Vietnam continua contribuyendo a la paz en la frontera entre Tailandia y Camboya

|

Vietnam da la bienvenida a los desarrollos positivos entre Camboya y Tailandia y continuara esforzandose por contribuir a la paz en las fronteras de los dos paises.

Hanoi tiene dos semanas para entregar la tierra suficiente para la carretera de la Franja 4

HỮU CHÁNH |

Hanoi - Los distritos y distritos deben completar la liberacion de la superficie del proyecto de la Zona 4 antes del 15.4 bajo la direccion del Presidente de la Junta de la ciudad.

Puente sobre el rio, ferrocarril en la Zona 4 de Hanoi en forma

HỮU CHÁNH |

Hanoi - Tres puentes que cruzan el rio, el proyecto de ferrocarril de la ruta paralela de la Franja de 4 tramos a traves del distrito de Meilin ya ha aparecido y esta siendo terminado.

Hà Nội thu hồi đất làm Vành đai 1, thúc tiến độ Vành đai 4

HỮU CHÁNH |

Hà Nội đang tập trung thu hồi đất thi công đường Vành đai 1 đoạn Hoàng Cầu - Voi Phục, thúc tiến độ đường song hành Vành đai 4 hoàn thành trong quý IV/2025.