Can Tho - The Inspectorate pointed out many limitations and shortcomings in the project to upgrade and expand the Rach Cam bridge route and the Binh Thuy Primary School project.

Can Tho City Inspectorate has just issued a conclusion, pointing out limitations and shortcomings for the project to upgrade and expand the Rach Cam bridge route and the Binh Thuy Primary School project invested by the People's Committee of Binh Thuy District in the period of 2021-2023.

According to the conclusion, Can Tho City Inspectorate has clearly pointed out the decision to approve the investment policy of upgrading and expanding the Rach Cam Bridge route and the Binh Thuy Primary School project is not in accordance with the authority according to Resolution No. 01. The reason is that the advisory department does not know the regulations on the authority to issue documents.

Thanh tra thanh pho Can Tho. Anh: Ta Quang
Can Tho City Inspectorate. Photo: Ta Quang

Regarding the contractor selection plan that has not been appraised before issuance, it is not in accordance with regulations; not publicly posted to the national bidding network according to regulations (project to upgrade and expand the Rach Cam bridge route).

The work of preparing, appraising and approving the Economic - Technical Report for the project to upgrade and expand the Rach Cam bridge route is still limited and lacking; The estimate of some items of the 2 projects with excess volume with a total amount of more than 66 million VND.

The investor has not publicly posted the results of contractor selection for the designated packages on the national bidding network. The contractor drafted a construction contract and sent it to the investor, which was not in accordance with the shortened bidding instructions.

The appraisal and approval of bidding documents was carried out within 1 day, which was not in accordance with the time. The expert team assessed that the key personnel of the bidding documents were not in accordance with the standards prescribed for the bidding documents.

In addition, the contractor participating in the bidding provided dishonest information for the Binh Thuy Primary School project.

The construction unit changed the construction method but there was no opinion from the investor and related units; the acceptance and settlement of the contract was over the actual construction volume with a total value of more than 670 million VND.

The construction supervision unit has not fully exercised the rights and obligations of the contractor supervising the construction of the project according to regulations. Electing supervisors with inappropriate expertise to participate in volume acceptance is not guaranteed according to the provisions of the Construction Law.

The Binh Thuy Primary School project was accepted and put into use before the competent authority's announcement of the results of the inspection of the completion of the project items was not suitable.

The City Inspectorate recommended that the Chairman of the City People's Committee direct the Chairman of the Binh Thuy District People's Committee to overcome the above limitations, shortcomings, and violations and organize a review and consideration of responsibilities for related individuals.

Tạ Quang
Noticias relacionadas

Progreso de la organizacion, la fusion de las comunas en el Pacifico, Ba Ria - Vung Tau, Can Tho

|

Las localidades como Binh Duong, Ba Ria-Vung Tau, Can Tho... estan acelerando el proceso de ordenamiento, uniendo las unidades administrativas a nivel de comuna.

Proyecto VSIP mas de 3.700 millones de dolares en la necesidad de la falta de arena de relleno

|

El proyecto Can Tho VSIP Industrial Park es tambien el parque industrial mas grande de la ciudad con una inversion total de mas de VND 3,700 mil millones, enfrentando una gran barrera por la escasez de nivelar material de arena.

El secretario y el presidente Chen Tsu examinaron el trayecto de 9.700 millones de VND

|

Necesitamos un lider local que se conecte con la provincia de An Giang, Tien Giang para resolver el problema de la arena, movilizar recursos humanos y equipos para acelerar el progreso.

El trabajo de formacion de voleibol juvenil en Vietnam necesita un gran avance

|

El trabajo de seleccion y formacion de jovenes atletas de voleibol vietnamitas enfrenta muchas dificultades por razones objetivas y subjetivas.

Ex presidente de Brasil sentenciado a 27 años de prision por conspirar para un golpe de estado

|

El Tribunal Supremo de Brasil condeno al ex presidente Jair Bolsonaro por conspiracion para derrocar los resultados electorales de 2022 a una pena de 27 años de prision.

Luces gigantes de la luna de miel de cientos de millones de VND brillantes en la ciudad de Tuyen Quang

|

Tuyen Quang - El festival de Trung thu en Tuyen Quang es famoso por sus enormes linternas.

No permitir la congestion de proyectos electricos debido a los retrasos en los tramites administrativos

|

El Viceprimer Ministro solicito a 3 corporaciones y 1 empresa militar que implementen resueltamente el proyecto electrico y no permitan la congestion del proyecto electrico debido a los retrasos en los procedimientos administrativos.

El marido se va a trabajar lejos la esposa en casa es infiel y tiene hijos con otra persona - Parte 1

|

Hora 9 - El marido expatriado se va a trabajar lejos y envia dinero para mantener a su familia. Pero en la soledad la esposa es infiel y esta embarazada de otra persona. ¿Como sera esta familia?

Progreso de la organizacion, la fusion de las comunas en el Pacifico, Ba Ria - Vung Tau, Can Tho

PHẠM ĐÔNG |

Las localidades como Binh Duong, Ba Ria-Vung Tau, Can Tho... estan acelerando el proceso de ordenamiento, uniendo las unidades administrativas a nivel de comuna.

Proyecto VSIP mas de 3.700 millones de dolares en la necesidad de la falta de arena de relleno

TẠ QUANG |

El proyecto Can Tho VSIP Industrial Park es tambien el parque industrial mas grande de la ciudad con una inversion total de mas de VND 3,700 mil millones, enfrentando una gran barrera por la escasez de nivelar material de arena.

El secretario y el presidente Chen Tsu examinaron el trayecto de 9.700 millones de VND

Tạ Quang |

Necesitamos un lider local que se conecte con la provincia de An Giang, Tien Giang para resolver el problema de la arena, movilizar recursos humanos y equipos para acelerar el progreso.